Legislation Details

File #: 25-2857   
Status: Passed
File created: 8/28/2025 In control: Clark County Board of Commissioners
On agenda: 9/16/2025 Final action: 9/16/2025
Title: Approve and authorize the County Manager or his designee to sign Supplemental No. 3 to the professional engineering services contract between Clark County and WSP USA Inc. (Kaushal Shah, P.E., Senior Vice President, Local Business Leader) for additional engineering services for the Harmon Avenue between Maryland Parkway and Boulder Highway project. (For possible action)
Attachments: 1. Staff Report, 2. Supplemental No. 3 - Harmon Ave, Maryland Pkwy to Boulder Hwy - WSP USA, Inc.

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the County Manager or his designee to sign Supplemental No. 3 to the professional engineering services contract between Clark County and WSP USA Inc. (Kaushal Shah, P.E., Senior Vice President, Local Business Leader) for additional engineering services for the Harmon Avenue between Maryland Parkway and Boulder Highway project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4180.003

Fund Name:

MTP-Non Resort Corridor

Fund Center:

1260110001

Funded PGM/Grant:

PW.N191231

Amount:

$53,100

Description:

Harmon - Maryland Pkwy to Boulder Hwy

Additional Comments:

Initial contract amount was $1,121,312.75. Supplemental No. 1 increase of $97,600 revised the contract value to $1,218,912.75. Supplemental No. 2 increase of $60,000 revised the contract value to $1,278,912.75. Supplemental No. 3 increase of $53,100 revises the total contract value to $1,332,012.75.

 

BACKGROUND: 

On June 16, 2020, the Board of County Commissioners approved a professional engineering services contract with WSP USA Inc. for engineering services for design of the Harmon Avenue between Maryland Parkway and Boulder Highway project.

Supplemental No. 3 to the professional engineering services contract with WSP USA, Inc increases total funds for design revisions to the Maryland Parkway to Pecos Road Phase plans at Spencer Street, development of an alternative drainage design on Harmon Avenue from Spencer Street to Carriage Lane, and record drawings for the Maryland Parkway to Pecos Road Phase. The time of performance remains effective until December 31, 2025, unless further time extensions are granted.

WSP USA, Inc. currently holds a Clark County Business License.

The District Attorney's Office has reviewed and approved this third supplemental contract as to form.