title
Approve the award of Bid No. 606699-23, for Hollywood Boulevard Extension Phase 1 - Galleria Drive to Wetlands Park to the low responsive and responsible bidder, contingent upon submission of the required bonds and insurance. Staff recommends award to Las Vegas Paving Corporation; or take other action as appropriate. (For possible action)
body
FISCAL IMPACT:
|
Fund #: |
4120.002 |
Fund Name: |
MTP - Countywide |
|
Fund Center: |
1260110001 |
Funded PGM/Grant: |
PW.BW21520 |
|
Amount: |
$12,300,000 |
|
Description: |
Hollywood Boulevard Extension Phase 1 - Galleria Drive to Wetlands Park |
|
Additional Comments: |
None |
BACKGROUND:
Bid No. 606699-23, for Hollywood Boulevard Extension Phase 1 - Galleria Drive to Wetlands Park was advertised on October 23, 2023 and opened on December 19, 2023. The Bid amounts are as follows:
BIDS RECEIVED: BID AMOUNTS:
Las Vegas Paving Corporation (NBE) $12,300,000.00
Holcim - SWR, Inc. (NBE) $13,393,496.85
William Charles, Inc. (NBE) $14,932,609.05
This Contract is located in the City of Henderson and Clark County, Nevada, beginning at the intersection of Galleria Drive and Wiesner Way and terminating at a roundabout east of the Old Silver Bowl Park. Additionally, the construction includes a 4-lane roadway with new pavement, sidewalk, curb and gutter, median islands, and roundabout; Construction of new access road connecting the roundabout to the Old Silver Bowl Park; Concrete barrier and retaining wall along the west side of Wiesner Way; Removal and replacement of pavement and parking at the Old Silver Bowl Park; Street lighting, pavement markings, signage, ITS conduit and utility adjustments and relocations; Traffic signal poles and underground conduits at Galleria Drive and Wiesner Way and Hollywood Boulevard and Russell Road; Storm drainage facilities including drop inlets and pipes connecting to Wiesner Channel; Concrete transition structure and reinforced concrete box (RCB) connecting to the Wiesner Channel; Riprap channel along the west side of Old Silver Bowl Park.
The following are the pertinent provisions of the Contract:
• The Contractor shall complete the entire work within 365 calendar days from the date specified in the Notice to Proceed.
• Includes the standard termination for cause within 7 business days and termination for convenience language as in all public works efforts of this type.
The recommendation of award is in accordance with NRS 338.1385.5, a public body or its authorized representative shall award a contract to the lowest responsive and responsible bidder.
Las Vegas Paving Corporation currently holds a Clark County Business License.