CLARK COUNTY BOARD OF COMMISSIONERS
AGENDA ITEM
|
Petitioner: |
Jessica Colvin, Chief Financial Officer Denis Cederburg, Director of Public Works |
Recommendation:
title
Reject all Bids received for Bid No. 606680-23, for Flamingo Wash, Maryland Parkway to Palos Verdes Street; or take other action as appropriate. (For possible action)
body
FISCAL IMPACT:
|
Fund #: |
N/A |
Fund Name: |
N/A |
|
Fund Center: |
N/A |
Funded PGM/Grant: |
N/A |
|
Amount: |
N/A |
|
Description: |
N/A |
|
Additional Comments: |
None |
BACKGROUND:
Bid No. 606680-23, for Flamingo Wash, Maryland Parkway to Palos Verdes Street was advertised on November 7, 2023, and opened on June 11, 2024. 2 Bids were received and the Bid Amounts are as follows:
BIDS RECEIVED: BID AMOUNTS:
MMC, Inc. (NBE) $24,667,808
Las Vegas Paving Corporation (NBE) $34,000,000
This Contract is for channel improvements for the Flamingo Wash and Tropicana Wash located between Maryland Parkway and Palos Verdes Street including, reinforced concrete channel and culvert extensions from the four 12-foot by 12-foot reinforced concrete box under Maryland Parkway to the three 12-foot by 10-foot under Cambridge Street, concrete channel and culvert extensions from the three 10-foot by 7-foot RCB under University Center Avenue to the five 12-foot by 8-foot RCB under Palos Verdes Street, construction of a concrete lid for the Tropicana Wash north of Flamingo Road, a paved trail along the north side of the Flamingo Wash, maintenance roads and access ramps. Improvements will generally consist of reinforced concrete channel, storm drain facilities, reinforced concrete box, reinforced concrete pipes, drop inlets, manholes, asphaltic concrete pavement, fencing, conduit, pull boxes, signage, striping and monitoring equipment, and other related items of work within the unincorporated area of Clark County, Nevada.
All Bids received for the above referenced project are recommended for rejection. All bids came in over budget. A new Invitation for Bid for this effort will be issued in the near future with a revised scope of work to better meet the funds available for this project.