Title: Approve the award of Bid No. 607931-26, for Spring Mountain Road Phase 2 - Rainbow Boulevard and Decatur Boulevard to the low responsive and responsible bidder, contingent upon submission of the required bonds and insurance. Staff recommends award to Unicon, LLC; or take other action as appropriate. (For possible action)
Attachments: 1. Staff Report, 2. 607931-26 Disclosure
Date Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Jessica Colvin, Chief Financial Officer Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve the award of Bid No. 607931-26, for Spring Mountain Road Phase 2 - Rainbow Boulevard and Decatur Boulevard to the low responsive and responsible bidder, contingent upon submission of the required bonds and insurance. Staff recommends award to Unicon, LLC; or take other action as appropriate. (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Regional Imp Fund - RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R001JFT

Amount:

$5,685,000

Description:

Spring Mountain Road Phase 2 - Rainbow Boulevard and Decatur Boulevard

Additional Comments:

None

 

BACKGROUND: 

Bid No. 607931-26, for Spring Mountain Road Phase 2 - Rainbow Boulevard and Decatur Boulevard was advertised on May 6, 2026, and opened on June 8, 2026.  The Bid amounts are as follows:

BIDS RECEIVED:   
                                                                                                                                                   BID AMOUNTS:

Unicon, LLC (NBE)
                                                                                                                                                   $5,685,000.00
Monument Construction (NBE)
                                                                                                                              $5,826,200.00
Las Vegas Paving Corporation (NBE)
                                                                                                         $6,150,000.00
Amrize Southwest (NBE)
                                                                                                                              $6,258,074.70
Tand, Inc. (NBE)
                                                                                                                                                   $6,679,505.00
CG&B Enterprises, Inc. (NBE)
                                                                                                                              $6,794,777.00

This Contract is for improvements to Spring Mountain Road Phase 2 from Rainbow Boulevard to Decatur Boulevard. Improvements include mill and overlay of asphalt pavement, pavement reconstruction, raised center medians, driveway replacements, Americans with Disabilities (ADA) upgrades, improvements to existing street lighting, traffic signal modifications, intelligent transportation system (ITS) infrastructure, replacement of existing signage, utility modifications and adjustments, traffic control devices and pavement markings.

The following are the pertinent provisions of the Contract:
                     The Contractor shall complete the entire work within 200 calendar days from the date specified in the                      Notice to Proceed.
                     Includes the standard termination for cause within 7 business days and termination for convenience                      language as in all public works efforts of this type.

The recommendation of award is in accordance with NRS 338.1385.5, a public body or its authorized representative shall award a contract to the lowest responsive and responsible bidder.

Unicon, LLC currently holds a Clark County Business License.