File #: 26-1325   
Status: Agenda Ready
File created: 2/26/2026 In control: Clark County Board of Commissioners
On agenda: 3/17/2026 Final action:
Title: Approve and authorize the Chair to sign Supplemental No. 4 to Interlocal Contract No. 1025 between Clark County and Regional Transportation Commission of Southern Nevada to decrease total funds for design of the Cactus Avenue between Fort Apache Road and Buffalo Drive project. (For possible action)
Attachments: 1. Staff Report, 2. RTC Supplemental No. 4 to ILC 1025 - Cactus Ave, Ft. Apache Rd to Buffalo Dr.
Date Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 4 to Interlocal Contract No. 1025 between Clark County and Regional Transportation Commission of Southern Nevada to decrease total funds for design of the Cactus Avenue between Fort Apache Road and Buffalo Drive project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R147BFT

Amount:

$(150,000)

Description:

Cactus Ave - Ft. Apache Rd to Buffalo Dr

Additional Comments:

Initial contract amount was $1,500,000 and Supplemental No. 1 amount increased  contract by $335,500. Supplemental No. 2 increase of $235,000 revised the total  contract value to $2,070,500. Supplemental No. 3 extended the contract term. Supplemental No. 4 decrease of $150,000 revises the total contract value to $1,920,500.

 

BACKGROUND: 

On August 9, 2018, the Regional Transportation Commission of Southern Nevada (RTC) approved the Cactus Avenue between Fort Apache Road and Buffalo Drive project on its annual Capital Improvement Program initially from Fuel Revenue Indexing Extension Funds. The Board of County Commissioners approved this contract on September 4, 2018.

Supplemental No. 4 to Interlocal Contact No. 1025 decreases design funds, as the project is nearing completion. The term of the contract remains effective until June 30, 2028, unless time extensions are granted.

RTC has prepared Supplemental No. 4 to Interlocal Contract No. 1025 for the Board's consideration. RTC approved the fourth supplemental contract at its meeting on February 12, 2026.

The District Attorney's Office has reviewed and approved the fourth supplemental contract as to form.