File #: 26-2076   
Status: Agenda Ready
File created: 8/17/2026 In control: Clark County Board of Commissioners
On agenda: 9/1/2026 Final action:
Title: Approve and authorize the County Manager or his designee to sign Supplemental No. 2 to the professional engineering services contract between Clark County and Jacobs Engineering Group Inc. (Ken Gilbreth, P.E., Vice President) for additional engineering services and to extend the contract term for the Spring Mountain Road between Rainbow Boulevard and Aldebaran Avenue project. (For possible action)
Attachments: 1. Staff Report, 2. Supplemental No. 2 - Spring Mountain Rd, Rainbow to Aldebaran - Jacobs
Date Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the County Manager or his designee to sign Supplemental No. 2 to the professional engineering services contract between Clark County and Jacobs Engineering Group Inc. (Ken Gilbreth, P.E., Vice President) for additional engineering services and to extend the contract term for the Spring Mountain Road between Rainbow Boulevard and Aldebaran Avenue project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4180.003

Fund Name:

Non-Resort Corridor

Fund Center:

1260110001

Funded PGM/Grant:

PW.N220713

Amount:

$300,000

Description:

Spring Mountain - Rainbow to Aldebaran

Additional Comments:

Initial contract amount was $1,400,000. Supplemental No. 1 extended the contract term. Supplemental No. 2 increase of $300,000 revises the total contract value to $1,700,000.

 

BACKGROUND: 

On November 15, 2022, the Board of County Commissioners approved a professional engineering services contract with Jacobs Engineering Group Inc. for engineering services for design of the Spring Mountain Road between Rainbow Boulevard and Aldebaran Avenue project.

Supplemental No. 2 to the professional services contract will provide additional funds to perform design engineering services to analyze the impacts of modifying the existing roadway configuration to eliminate one westbound lane between Rainbow Boulevard and Aldebaran Avenue, separate the Spring Mountain Road from Rainbow Boulevard to Aldebaran Avenue project into two separate construction packages and provide a complete construction package for the Phase 2 segment from Rainbow Boulevard to Decatur Boulevard, and provide an expedited final design for a pedestrian crossing signal between Arville Street and Wynn Road as Phase 1 of the project. Supplemental No. 2 also extends the time of performance to December 31, 2028, unless further extensions are granted.

Jacobs Engineering Group Inc. currently holds a Clark County Business License.

The District Attorney's Office has reviewed and approved the second supplemental contract as to form.