Skip to main content
File #: 25-2864   
Status: Passed
File created: 8/28/2025 In control: Clark County Board of Commissioners
On agenda: 10/7/2025 Final action: 10/7/2025
Title: Receive notice regarding Change Order No. 1 to the contract with Holcim-SWR, Inc. for construction of the Residential Streets Pavement Reconstruction #105 Lot 1 project (Bid No. 607057-24). (For possible action)
Attachments: 1. Staff Report

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Receive notice regarding Change Order No. 1 to the contract with Holcim-SWR, Inc. for construction of the Residential Streets Pavement Reconstruction #105 Lot 1 project (Bid No. 607057-24).  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

2020.000 4180.003

Fund Name:

Road Fund Non-Resort Corridor

Fund Center:

1260110001

Funded PGM/Grant:

PW.P_Rehab PW.N15173A

Amount:

$2,834,000

Description:

Residential Streets Pavement Reconstruction #105 Lot 1

Additional Comments:

Initial contract amount was $18,252,172.05. Change Order No. 1 increases the contract by $2,834,000 and revises the total contract value to $21,086,172.05.

 

BACKGROUND: 

On December 3, 2024, the Board of County Commissioners approved the contract award of Bid No. 607057-24 in the amount of $18,252,172.05, to Holcim-SWR, Inc. for the Residential Streets Pavement Reconstruction #105 Lots 1 & 2 project.

Change Order No. 1 for $2,834,000 increases the total project funding to $21,086,172.05, providing funds for added scope of work on Christy Lane and Palm Street. Additional work on Christy Lane is between Bonanza Road and 200 feet south of Harris Avenue. Additional work on Palm Street is between Fremont Street and Sahara Avenue.