Title: Approve and authorize the County Manager or his designee to sign Supplemental No. 5 to the professional engineering services contract between Clark County and WSP USA Inc. (Kaushal Shah, P.E., Senior Vice President) for additional engineering services and to extend the contract term for the Hollywood Boulevard Extension between Vegas Valley Drive and Galleria Drive project. (For possible action)
Attachments: 1. Staff Report, 2. Supplemental No. 5 - Hollywood Blvd Extension, Vegas Valley Dr to Galleria Dr - WSP USA, Inc

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the County Manager or his designee to sign Supplemental No. 5 to the professional engineering services contract between Clark County and WSP USA Inc. (Kaushal Shah, P.E., Senior Vice President) for additional engineering services and to extend the contract term for the Hollywood Boulevard Extension between Vegas Valley Drive and Galleria Drive project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4120.002

Fund Name:

MTP Capital

Fund Center:

1260110001

Funded PGM/Grant:

PW.BW21520

Amount:

$1,217,200

Description:

Hollywood Blvd Extension - Vegas Valley to Galleria

Additional Comments:

Initial contract amount was $1,591,300. Supplemental Nos. 1 through 4 combined amounts increased the contract by $5,326,335. Supplemental No. 5 increase of $1,217,200 revises the total contract value to $8,134,835.

 

BACKGROUND: 

On August 4, 2020, the Board of County Commissioners approved the original professional engineering services contract between Clark County and WSP USA Inc. for professional engineering services for the Hollywood Boulevard Extension between Vegas Valley Drive and Galleria Drive project.

Supplemental No. 5 to the professional engineering services contract with WSP USA Inc. increases total funds for the Hollywood Boulevard Extension from Vegas Valley Drive to the Las Vegas Wash for the final design services on this phase of the project, and additional coordination efforts with surrounding properties. This fifth supplemental contract also extends the time of performance until December 31, 2027, unless further time extensions are granted.

WSP USA Inc. currently holds a Clark County Business License.

The District Attorney's Office has reviewed and approved the fifth supplemental contract as to form.