File #: 22-0134   
Status: Agenda Ready
File created: 1/13/2022 In control: Clark County Board of Commissioners
On agenda: 2/1/2022 Final action:
Title: Approve and authorize the County Manager or her designee to sign Supplemental No. 3 to the professional engineering services contract between Clark County and CH2M Hill Engineers, Inc. (Ken Gilbreth, P.E., Vice President) for additional engineering for the Tropicana Avenue/University Center Drive Grade Separation project. (For possible action)
Attachments: 1. Staff Report, 2. Supp 3 Contract CH2M Hill TropicanaUniversityCtrGradeSep

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the County Manager or her designee to sign Supplemental No. 3 to the professional engineering services contract between Clark County and CH2M Hill Engineers, Inc. (Ken Gilbreth, P.E., Vice President) for additional engineering for the Tropicana Avenue/University Center Drive Grade Separation project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4180.001

Fund Name:

MTP Room Tax -  Strip Resort Corridor

Fund Center:

1260110001

Funded PGM/Grant:

PW.S160824

Amount:

$2,000,687

Description:

Tropicana Ave/University Center Dr Grade Separation / Elevated Airport Express

Additional Comments:

Initial contract amount was $2,264,681; Supplemental No. 1 increased by $2,694,019; and Supplemental No. 2 increased by $5,838,300.  Supplemental No. 3 increase of $2,000,687 revises the total contract value to $12,797,687.

 

BACKGROUND: 

On September 6, 2016, the Board of County Commissioners approved a professional engineering services contract with CH2M Hill Engineers, Inc. for the evaluation of alternatives for pre-design of the elevated and at-grade limited access airport Outbound Elevated Expressway project (now known as the Tropicana Avenue/University Center Drive Grade Separation project).  At the conclusion of the pre-design work, it was determined to proceed with a grade separated intersection at the intersection of Tropicana Avenue and Swenson Street, and an underpass at Paradise Road.

The Board previously approved two supplementals to the professional engineering services contract with CH2M Hill Engineers, Inc.  Supplemental No. 1 provided for the final design of the grade separation structure and the underpass at Paradise Road.  Subsequent analysis of alternatives and additional stakeholder input resulted in a grade separation of the Tropicana Avenue/University Center Drive with Tropicana Avenue being below-grade and University Center Drive remaining at-grade.  Supplemental No. 2 provided engineering services for the design of the Tropicana Avenue below-grade alternative.

The attached Supplemental No. 3 to the professional services contract with CH2M Hill Engineers, Inc. is for the design of a pedestrian bridge, a bridge, and access to the TNC lot, additional geotechnical and ground water investigation, Intelligent Transportation System, and an Environmental Analysis required by the Federal Aviation Administration.

CH2M Hill Engineers, Inc. currently holds a Clark County Business License.

The District Attorney's Office has reviewed and approved the third supplemental contract as to form.