File #: 24-993   
Status: Agenda Ready
File created: 7/2/2024 In control: Clark County Board of Commissioners
On agenda: 7/16/2024 Final action:
Title: Approve a Change Order to the Contract with SHF International, LLC, for Bid No. 606920-23, for Russell Campus Building & Fire Prevention Covered Parking; and authorize the Chief Financial Officer or her designee to sign the Change Order; or take other action as appropriate. (For possible action)
Attachments: 1. Staff Report, 2. B606920-23 Change Order

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Jessica Colvin, Chief Financial Officer Shauna Bradley, Deputy Director of Real Property Management

Recommendation: 

title

Approve a Change Order to the Contract with SHF International, LLC, for Bid No. 606920-23, for Russell Campus Building & Fire Prevention Covered Parking; and authorize the Chief Financial Officer or her designee to sign the Change Order; or take other action as appropriate. (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

5340.000

Fund Name:

Building

Fund Center:

1120820001

Funded PGM/Grant:

RP.A0322046

Amount:

$1,211,897.16

Description:

Russell Campus Building & Fire Prevention Covered Parking

Additional Comments:

The initial Contract amount was $5,016,029, Change Order No. 1 had no fiscal impact, Change Order No. 2 will increase the Contract amount by $1,211,897.16, for a new total Contract amount of $6,227,926.16.

 

BACKGROUND: 

On March 5, 2024, the Board of County Commissioners (Board) approved the award of Bid No. 606920-23 for Russell Campus Building & Fire Prevention Covered Parking to SHF International, LLC (NBE) in the amount of $5,016,029 for the construction of a 3-phased new covered parking area to the existing employee parking lot. Scope of work included landscape removal, hydro excavating, saw cutting, asphalt removal and disposal for a new painted metal deck covered parking structure with cast-in-place concrete caisson footings and installed light fixtures under new covered parking structure.

The following are the pertinent provisions of the Contract:
                     The Contractor shall complete the entire work within 390 calendar days from the date specified after the                      receipt of the Notice to Proceed. 
                     Included the standard termination for cause within 7 business days and termination for convenience                      language as in all public works efforts of this type.

Change Order No. 1 provided for all labor, material, equipment, and services to expedite phase 1, 2 and 3 shop drawings and extended Contract by 97 calendar days.

Approval of Change Order No. 2 will provide for the design and upgrade of the structural I-beam carports.  The attached Change Order No. 2 document details the modifications and costs involved.

SHF International, LLC currently holds a Clark County Business License.