Skip to main content
File #: 22-0416   
Status: Agenda Ready
File created: 3/21/2022 In control: Clark County Board of Commissioners
On agenda: 4/5/2022 Final action:
Title: Approve and authorize full lane closures on Las Vegas Boulevard and Flamingo Road together with full or partial lane closures on Koval Lane from April 13 through May 6 for set-up and breakdown operations for the 2022 National Football League (NFL) Draft to be held April 27 through April 30 in Las Vegas, Nevada. (For possible action)
Attachments: 1. Staff Report

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize full lane closures on Las Vegas Boulevard and Flamingo Road together with full or partial lane closures on Koval Lane from April 13 through May 6 for set-up and breakdown operations for the 2022 National Football League (NFL) Draft to be held April 27 through April 30 in Las Vegas, Nevada.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

N/A

Fund Name:

N/A

Fund Center:

N/A

Funded PGM/Grant:

N/A

Amount:

N/A

Description:

N/A

Additional Comments:

N/A

 

BACKGROUND: 

The 2022 NFL Draft will be held in Las Vegas from April 28 through April 30.

On January 21, 2020, the Board of County Commissioners discussed possible lane closures related to the 2022 NFL Draft (Agenda Item #56).  On February 1, 2022, the Board received a presentation (Agenda Item #55) from representatives of the NFL.  Today's agenda item requests approval for lane closures on Las Vegas Boulevard and Flamingo Road, along with ancillary streets, in conjunction with this three-day event.

The full closures for the event will begin at 10:00 PM on April 27 and end at 9:00 PM on April 30.  The only overnight lanes to be open on April 29 and April 30 will be on Las Vegas Boulevard at Flamingo Road to the Bellagio Hotel entrance, and the southbound left-turn lanes and inside thru-lanes at Flamingo Road and Las Vegas Boulevard.

Starting April 13 for event set-up and concluding May 6 for event breakdown, lane closures will be in effect for the following roadways:  the outside eastbound lane from 200 feet west of Bellagio North Porte Cochere to the Bellagio North Porte Cochere; the outside eastbound lane from Bellagio North Porte Cochere through the outside lane of channelized right-turn at Las Vegas Boulevard; the southbound curb lane on Koval Lane from Winnick Avenue to Krueger Drive; and the two outside lanes from Flamingo Road to the Bellagio Hotel entrance.  Between the hours of 6:00 AM and 5:00 PM, a third lane closure will be implemented on Las Vegas Boulevard from the outside southbound lanes from Flamingo Road to the Bellagio Hotel entrance.