File #: 23-1628   
Status: Agenda Ready
File created: 11/16/2023 In control: Clark County Board of Commissioners
On agenda: 12/5/2023 Final action:
Title: Approve and authorize the Chair to sign Interlocal Contract No. 3122 between Clark County and Regional Transportation Commission of Southern Nevada for construction of the Maryland Parkway Underground Utilities between Tropicana Avenue and Flamingo Road project. (For possible action)
Attachments: 1. Staff Report, 2. RTC Interlocal Contract 3122 Maryland Pkwy Underground Utilities, Tropicana to Flamingo

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Interlocal Contract No. 3122 between Clark County and Regional Transportation Commission of Southern Nevada for construction of the Maryland Parkway Underground Utilities between Tropicana Avenue and Flamingo Road project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R256AFT

Amount:

$14,000,000

Description:

Maryland Pkwy Underground Utilities - Tropicana to Flamingo

Additional Comments:

N/A

 

BACKGROUND: 

The Regional Transportation Commission of Southern Nevada (RTC) has approved and budgeted funding for the Maryland Parkway Underground Utilities between Tropicana Avenue and Flamingo Road project in the Highway Improvement Acquisition Fund - Fuel Revenue Indexing for Fiscal Year 2024. All necessary rights-of-way to construct the project have been obtained.

Interlocal Contract No. 3122 allocates funds for construction of the Maryland Parkway Underground Utilities between Tropicana Avenue and Flamingo Road project. The project consists of improvements on Maryland Parkway from 650 feet south of Tropicana Avenue to 200 feet north of Flamingo Road, a length of approximately one mile. The project includes installing a shared utility conduit duct bank to facilitate the undergrounding of overhead utility lines on the east side of Maryland Parkway. The time of performance is effective until December 31, 2028, unless time extensions are granted.

RTC approved the interlocal contract at its meeting on November 9, 2023.

The District Attorney's Office has reviewed and approved the interlocal contract as to form.