Title: Approve and authorize the Chair to sign Interlocal Contract No. 3257 between Clark County and Regional Transportation Commission of Southern Nevada for construction of the Spring Mountain Road between Rainbow Boulevard and Decatur Boulevard project. (For possible action)
Attachments: 1. Staff Report, 2. RTC Interlocal Contract No. 3257 - Spring Mountain Rd, Rainbow Blvd to Decatur Blvd
Date Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Interlocal Contract No. 3257 between Clark County and Regional Transportation Commission of Southern Nevada for construction of the Spring Mountain Road between Rainbow Boulevard and Decatur Boulevard project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R001JFT

Amount:

$15,000,000

Description:

Spring Mountain Rd - Rainbow Blvd to Decatur Blvd

Additional Comments:

N/A

 

BACKGROUND: 

The Regional Transportation Commission of Southern Nevada (RTC) has approved the Spring Mountain Road between Rainbow Boulevard and Decatur Boulevard project on its annual Capital Improvement Program from its Highway Improvement Acquisition Fund - Fuel Revenue Indexing for Fiscal Year 2026.

Interlocal Contract No. 3257 provides funds for construction of the subject project. The work to be performed on Spring Mountain Road between Rainbow Boulevard and Decatur Boulevard includes roadway mill and overlay, traffic signal and intelligent transportation systems (ITS) improvements, traffic signage, streetlight upgrades, pavement markings, utility adjustments, and other miscellaneous improvements. The design for the project was funded by Clark County. The design is at least 90 percent complete, and all necessary right-of-way to construct the project has been obtained. The term of the contract is effective until June 30, 2031, unless time extensions are granted.

RTC has prepared Interlocal Contract No. 3257 for the Board's consideration. RTC approved the interlocal contract at its meeting on March 12, 2026.

The District Attorney's Office has reviewed and approved the interlocal contract as to form.