CLARK COUNTY BOARD OF COMMISSIONERS
AGENDA ITEM
Petitioner: |
Rosemary A. Vassiliadis, Director of Aviation |
Recommendation:
title
Approve the award of Project 3032 LAS Holding Pad 7 and Main Gate (Project) and authorize the Director of Aviation to sign the contract contingent upon the contractor providing both labor and material bond and a performance bond as required by the contract documents; staff recommends award of the bid to TAB Contractors, Inc. (Mark Urban, Vice President), the lowest responsive and responsible bidder; or take other action as appropriate. (For possible action)
body
FISCAL IMPACT:
Fund #: |
5202.731 |
Fund Name: |
Airport Projects Cash & Investments |
Fund Center: |
2200700020 |
Funded PGM/Grant: |
FAA Bipartisan Infrastructure Law |
Amount: |
Not to Exceed $63,323,209 |
Description: |
Award of Contract to TAB Contractors, Inc. |
Additional Comments: |
N/A |
BACKGROUND:
This project is located at Harry Reid International Airport and includes the reconstruction and expansion of aircraft holding pad 7, as well as reconstruction of the airfield Main Gate to improve Airport security. The existing holding pad 7 surfaces are constructed of both Asphalt Concrete (AC) and Portland Cement Concrete (PCC). The surfaces have reached the appropriate timeframe for replacement. This Project will enable the replacement of the AC and PCC surfaces with new Airfield PCC pavement.
Bid was received and publicly opened on April 12, 2023:
BID RECEIVED SUBMITTED BID PRICE
TAB Contractors, Inc. $63,323,209.00
This award recommendation is in accordance with NRS 338.1385, award of contract to the lowest responsive and responsible bidder. TAB Contractors, Inc. currently holds a Clark County Business License.