File #: 22-0979   
Status: Agenda Ready
File created: 6/29/2022 In control: Clark County Board of Commissioners
On agenda: 7/19/2022 Final action:
Title: Approve and authorize the Chair to sign Supplemental No. 1 to the interlocal contract between Clark County and Clark County Regional Flood Control District to increase total funds for the Blue Diamond Wash between Arville Street and Interstate 15 project. (For possible action)
Attachments: 1. Staff Report, 2. Supp 1 Contract RFCD BlueDiamondWashArvilleI-15

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 1 to the interlocal contract between Clark County and Clark County Regional Flood Control District to increase total funds for the Blue Diamond Wash between Arville Street and Interstate 15 project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.992

Fund Name:

Public Works Regional Improvements/RFCD

Fund Center:

1260110001

Funded PGM/Grant:

PW.FCLA16Q

Amount:

$1,271,346

Description:

Blue Diamond Wash - Arville to I-15

Additional Comments:

Initial contract amount was $6,650,000.  Supplemental No. 1 increase in the amount of $1,271,346 revises the total contract value to $7,921,346.

 

BACKGROUND: 

The Regional Flood Control District (RFCD) has programmed funds for the design and construction of flood control improvements.  On November 18, 2021, Clark County and RFCD entered into an interlocal contract for the Blue Diamond Wash between Arville Street and Interstate 15 (I-15) project.  The Board of County Commissioners approved the interlocal contract on December 7, 2021.

The attached Supplemental No. 1 to the interlocal contract increases total funds for construction and construction management for the project.

This project is approved on RFCD's Ten-Year Construction Program, and described in its 2018 Clark County Flood Control Master Plan Update as Structure No. BDWA 0276.  RFCD approved the first supplemental contract at its meeting on June 9, 2022.

The District Attorney's Office has reviewed and approved the first supplemental contract as to form.