File #: 26-1031   
Status: Passed
File created: 12/18/2025 In control: Clark County Board of Commissioners
On agenda: 1/6/2026 Final action: 1/6/2026
Title: Approve and authorize the Chair to sign Supplemental No. 4 to the interlocal contract between Clark County and Regional Flood Control District to increase total funds and extend the contract term for design of the Flamingo, Cimarron Branch between Russell Road and Patrick Lane project. (For possible action)
Attachments: 1. Staff Report, 2. RFCD Supplemental No. 4 - Flamingo, Cimarron Branch - Russell Rd to Patrick Ln

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 4 to the interlocal contract between Clark County and Regional Flood Control District to increase total funds and extend the contract term for design of the Flamingo, Cimarron Branch between Russell Road and Patrick Lane project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.992

Fund Name:

Public Works Regional Improvements/RFCD

Fund Center:

1260110001

Funded PGM/Grant:

PW.FCLA01F

Amount:

$50,000

Description:

Flamingo, Cimarron Branch - Russell to Patrick

Additional Comments:

Initial contract amount was $520,000. Supplemental No. 1 reallocated funding. Supplemental No. 2 increase of $50,000 revised the total contract value to $570,000. Supplemental No. 3 increase of $50,000 revised the total contract value to $620,000. Supplemental No. 4 increase of $50,000 revises the total contract value to $670,000.

 

BACKGROUND: 

The Clark County Regional Flood Control District (RFCD) has programmed funds to design and construct flood control improvements. On August 12, 2021, the RFCD approved an interlocal contract for the Flamingo, Cimarron Branch between Russell Road and Patrick Lane project in its 2018 Clark County Flood Control Master Plan Update, Structures No. FLCM 0003. The Board of County Commissioners approved this contract on September 21, 2021.

Supplemental No. 4 to the interlocal contract extends the project completion date from June 30, 2026 to December 31, 2027, and increases entity labor funds.

RFCD approved the fourth supplemental contract at its meeting on November 13, 2025.

The District Attorney's Office has reviewed and approved the fourth supplemental contract as to form.