Approve and authorize the County Manager or his designee to sign a professional engineering services contract between Clark County and GCW, Inc. (Tim McCoy, President) for engineering services for management, oversight, and review of individual improvement projects within the Clark County Public Works Capital Improvement Program. (For possible action)
body
FISCAL IMPACT:
|
Fund #: |
2020.000 4120.000 4180.000 4420.000 4990.990 |
Fund Name: |
Road Fund Master Transportation Plan Master Trans Room Tax Improvs Public Works Capital Construction Public Works Regional Improvs |
|
Fund Center: |
1260110001 |
Funded PGM/Grant: |
N/A |
|
Amount: |
$1,000,000 |
|
Description: |
PW Project Management |
|
Additional Comments: |
Services to be requested by work order, with funding from any of the above-mentioned sources. |
BACKGROUND:
CKGROUND:
On December 16, 2025, the Board of County Commissioners approved a pre-qualification list to be used to select professional service providers for the period of January 1, 2026 through December 31, 2027. Based on GCW, Inc's ranking in 10 of the design categories of Services and Works, GCW, Inc. was selected to provide professional engineering services on various projects in the Clark County Public Works Capital Improvement Program.
County staff negotiated the attached professional engineering services contract with GCW, Inc. The contract describes the services to be provided and stipulated terms. The time of performance is effective to December 31, 2028, unless time extensions are granted. This contract provides for individual public works capital improvement projects designed by separate engineering consultant firms to be managed and overseen by GCW, Inc.
GCW, Inc. currently holds a Clark County Business License.