File #: 23-144   
Status: Agenda Ready
File created: 1/18/2023 In control: Clark County Board of Commissioners
On agenda: 2/7/2023 Final action:
Title: Approve and authorize the General Manager to sign the Manhole and Valve Cover Agreement Letter for sanitary sewer manhole adjustments in the not-to-exceed amount of $27,600, as part of the Nevada Department of Transportation (NDOT) Project SPI-015-1(085) for the construction of Route I-15 at Tropicana Avenue interchange, grade separation at Tropicana Avenue and Dean Martin Drive, and HOV ramps at Harmon Avenue from MP CL 34.847 to MP CL 40.551; or take other action as appropriate. (For possible action)
Attachments: 1. Staff Report, 2. Manhole & Valve Cover Agreement Letter

CLARK COUNTY Water Reclamation District

Board of Trustees

AGENDA ITEM

 

Petitioner:

Thomas A. Minwegen, General Manager

Recommendation: 

title

Approve and authorize the General Manager to sign the Manhole and Valve Cover Agreement Letter for sanitary sewer manhole adjustments in the not-to-exceed amount of $27,600, as part of the Nevada Department of Transportation (NDOT) Project SPI-015-1(085) for the construction of Route I-15 at Tropicana Avenue interchange, grade separation at Tropicana Avenue and Dean Martin Drive, and HOV ramps at Harmon Avenue from MP CL 34.847 to MP CL 40.551; or take other action as appropriate. (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

Capital Funds

Fund Name:

CCWRD General Funds

Fund Center:

CCWRD Funds

Funded PGM/Grant:

N/A

Amount:

$27,600

Description:

Reimbursement to NDOT Contractor to adjust 4 manholes

Additional Comments:

N/A

 

BACKGROUND: 

The District has existing sanitary sewer assets located within the Tropicana Avenue, Dean Martin Drive, and Harmon Avenue right-of-way(s), which includes manholes and pipelines for wastewater conveyance to the Flamingo Water Resource Center. NDOT has scheduled Project SPI-015-1(085), for the construction of Route I-15 at Tropicana Avenue interchange, grade separation on Tropicana Avenue and Dean Martin Drive, and HOV ramps at Harmon Avenue from MP CL 34.847 to MP CL 40.551. During a roadway construction project, manholes are required to be adjusted prior to the installation of new paving, after which the manholes are then raised to the new elevated grade.

Pursuant to the District’s Right-of-Way Occupancy Permits, NRS 408.210 and 408.423, the District is required to pay for sanitary sewer manhole adjustments where NDOT has acquired prior rights to the right-of-way. The Manhole and Valve Cover Agreement Letter provides that NDOT's contractor will perform the manhole adjustments and then the District will pay for the associated costs, estimated to be five thousand dollars ($5,000.00) per manhole, plus an additional fee of between five percent (5%) and fifteen percent (15%) of the manhole costs for construction engineering and administration. Four (4) non-compensable manholes have been identified as needing adjustment within the NDOT project, with a twenty percent (20%) contingency for additional manholes (identified as part of Project SPI-015-01(085) after the date hereof) and/or volatile construction costs, which results in a total not-to-exceed cost of twenty-seven thousand six hundred dollars ($27,600).

Staff recommends that the Board approve and authorize the General Manager to sign the Manhole and Valve Cover Agreement Letter between NDOT and the District for sanitary sewer manhole adjustments.

This agenda item has been reviewed and approved by the District General Counsel.