Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 1 to Interlocal Contract No. 1283 between Clark County and Regional Transportation Commission of Southern Nevada to increase total funds for the Karen Avenue between Maryland Parkway and Flamingo Wash project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R254AFT

Amount:

$3,500,000

Description:

Karen - Maryland Pkwy to Flamingo Wash

Additional Comments:

Initial contract amount was $15,500,000.  Supplemental No. 1 increase of $3,500,000 revises the total contract value to $19,000,000.

 

BACKGROUND: 

On June 10, 2021, the Regional Transportation Commission of Southern Nevada (RTC) approved Interlocal Contract No. 1283, from its adopted Capital Improvement Plan, for construction of the Karen Avenue between Maryland Parkway and Flamingo Wash project.  The Board of County Commissioners approved this contract on July 6, 2021.  This project is budgeted in RTC's Highway Improvement Acquisition Fund - Fuel Revenue Indexing for Fiscal Year 2022.

The attached Supplemental No. 1 to Interlocal Contract No. 1283 increases total funds for project construction to cover increased costs due to bid amounts ranging higher than the Engineer's estimate.

RTC approved the first supplemental contract at its meeting on June 9, 2022.

The District Attorney's Office has reviewed and approved the first supplemental contract as to form.