File #: 23-1085   
Status: Agenda Ready
File created: 7/27/2023 In control: Clark County Board of Commissioners
On agenda: 8/15/2023 Final action:
Title: Approve and authorize the Chair to sign an interlocal contract between Clark County and Regional Flood Control District for construction of the Jim McGaughey Detention Basin, Collection and Outfall project. (For possible action)
Attachments: 1. Staff Report, 2. RFCD ILC Jim McGaughey Detention Basin, Collection and Outfall

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign an interlocal contract between Clark County and Regional Flood Control District for construction of the Jim McGaughey Detention Basin, Collection and Outfall project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.992

Fund Name:

Public Works Regional Improvements/RFCD

Fund Center:

1260110001

Funded PGM/Grant:

PW.FCLA36B

Amount:

$19,654,327

Description:

Jim McGaughey Detention Basin, Collection and Outfall

Additional Comments:

N/A

 

BACKGROUND: 

The Clark County Regional Flood Control District (RFCD) has approved and programmed funds for flood control improvements for the Jim McGaughey Detention Basin, Collection and Outfall project. The project is described in the 2018 Clark County Regional Flood Control District's Master Plan Update (MPU) as Structure Numbers SLWA 0130, 0140, 0150, 0151, 0152, 0153, 0175 and 0180, and SLOW 0000.

The attached interlocal contract will provide funds in Year 1 of RFCD's Ten-Year Construction Program for construction. The proposed construction improvements consist of an 88-acre detention basin, spillway, inflow, and outlet facilities.

The time of performance is effective until June 30, 2028, unless time extensions are granted.

RFCD approved the interlocal contract at its meeting on July 13, 2023.

The District Attorney's Office has reviewed and approved the interlocal contract as to form.