Legislation Details

File #: 26-2407   
Status: Agenda Ready
File created: 10/29/2026 In control: Clark County Board of Commissioners
On agenda: 11/17/2026 Final action:
Title: Approve and authorize the Chair to sign Supplemental No. 1 to Interlocal Contract No. 3217 between Clark County and Regional Transportation Commission of Southern Nevada to increase total funds for construction of the Residential Streets Pavement Reconstruction No. 106 project. (For possible action) 
Attachments: 1. Staff Report, 2. RTC Supplemental No. 1 to ILC 3217 - Residential Streets 106
Date Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 1 to Interlocal Contract No. 3217 between Clark County and Regional Transportation Commission of Southern Nevada to increase total funds for construction of the Residential Streets Pavement Reconstruction No. 106 project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R175ALF

Amount:

$650,000

Description:

Residential Streets Pavement Reconstruction #106

Additional Comments:

Initial contract amount was $15,500,000, and Supplemental No. 1 increase of $650,000 revises the total contract value to $16,150,000.

 

BACKGROUND: 

On May 22, 2025, the Regional Transportation Commission of Southern Nevada (RTC) and Clark County entered into Interlocal Contract No. 3217 for construction of the Residential Streets Pavement Reconstruction No. 106 project. The Board of County Commissioners approved the interlocal contract on June 17, 2025.

Supplemental No. 1 to Interlocal Contract No. 3217 will provide additional construction funds to cover the cost for Change Order No. 2 on the Contract, and for in-house labor. The time of performance remains effective until June 30, 2030, unless time extensions are granted.

RTC has prepared Supplemental No. 1 to Interlocal Contract No. 3217 for the Board's consideration. RTC approved the first supplemental contract at its meeting on October 8, 2026.

The District Attorney's Office has reviewed and approved the first supplemental contract as to form.