File #: 26-1320   
Status: Agenda Ready
File created: 2/26/2026 In control: Clark County Board of Commissioners
On agenda: 3/17/2026 Final action:
Title: Approve and ratify the grant submission by the Clark County Public Works Department for the Fiscal Year 2026 Better Utilizing Investments to Leverage Development (BUILD) Capital Grant through the United States Department of Transportation for the Spring Mountain Road Phase 3 between Decatur Boulevard and Aldebaran Avenue project; and authorize the County Manager or his designee to sign any grant documents and accept any funds awarded. (For possible action)
Attachments: 1. Staff Report
Date Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and ratify the grant submission by the Clark County Public Works Department for the Fiscal Year 2026 Better Utilizing Investments to Leverage Development (BUILD) Capital Grant through the United States Department of Transportation for the Spring Mountain Road Phase 3 between Decatur Boulevard and Aldebaran Avenue project; and authorize the County Manager or his designee to sign any grant documents and accept any funds awarded.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

N/A

Amount:

$24,450,000

Description:

Spring Mountain, Phase 3 - Decatur to Aldebaran

Additional Comments:

If awarded, funding will be provided by the United States Department of Transportation and RTC.

 

BACKGROUND: 

The Regional Transportation Commission of Southern Nevada (RTC) has worked alongside Clark County to apply for the Fiscal Year 2026 BUILD Capital Grant through the United States Department of Transportation.  If awarded, this grant would award Clark County $24,450,000 which is intended to be used for the Spring Mountain Road Phase 3 between Decatur Boulevard and Aldebaran Avenue project.

Design specifications estimate this project will cost approximately $48,900,000 and future funding will be needed.  The RTC has provided a Financial Commitment Letter stating that if the award is granted to Clark County, the remaining funding will be provided by the RTC.