File #: 24-615   
Status: Agenda Ready
File created: 4/25/2024 In control: Clark County Board of Commissioners
On agenda: 5/21/2024 Final action:
Title: Approve the award of Bid No. 606917-23, for Maryland Parkway Overhead Utility Undergrounding - Tropicana Avenue to Flamingo Road to the low responsive and responsible bidder, contingent upon submission of the required bonds and insurance. Staff recommends award to Byrd Underground, LLC; or take other action as appropriate. (For possible action)
Attachments: 1. Staff Report

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Jessica Colvin, Chief Financial Officer Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve the award of Bid No. 606917-23, for Maryland Parkway Overhead Utility Undergrounding - Tropicana Avenue to Flamingo Road to the low responsive and responsible bidder, contingent upon submission of the required bonds and insurance. Staff recommends award to Byrd Underground, LLC; or take other action as appropriate. (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Regional Transportation Improvements - RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R256BFT

Amount:

$10,339,926

Description:

Maryland Parkway Overhead Utility Undergrounding - Tropicana Avenue to Flamingo Road

Additional Comments:

None

 

BACKGROUND: 

Bid No. 606917-23, for Maryland Parkway Overhead Utility Undergrounding - Tropicana Avenue to Flamingo Road was advertised on January 30, 2024 and opened on February 26, 2024.  The Bid amounts are as follows:

BIDS RECEIVED:   
                                                                                                                                                   BID AMOUNTS:
Byrd Underground, LLC (NBE)
                                                                                                                              $10,339,962.00
Team Fishel (The Fishel Company) (NBE)
                                                                                    $14,370,218.50
Las Vegas Paving Corporation (NBE)
                                                                                                         $15,350,000.00
                     
This Contract is for improvements on Maryland Parkway from 650 feet south of Tropicana Avenue to 200 feet north of Flamingo Road, a length of approximately one mile. The project includes installing a shared utility conduit duct bank to facilitate the undergrounding of overhead utility lines on the east side of Maryland Parkway. Transverse utility crossings requested by the utilities will be also installed. Existing overhead utility lines to be undergrounded include NV Energy, Cox, and Lumen. Work will include removal and reconstruction of bituminous pavement, curb & gutter, sidewalk, raised median, and pavement markings, and adjustment/relocation of existing utilities. The work also consists of miscellaneous removal and disposal and removal and salvage/replacement of designated items, traffic control, dust control, quality control, and other related items of work as specified and shown on the drawings.

The following are the pertinent provisions of the Contract:
                     The Contractor shall complete the entire work within 180 calendar days from the date specified in the                      Notice to Proceed.
                     Includes the standard termination for cause within 7 business days and termination for convenience                      language as in all public works efforts of this type.

The recommendation of award is in accordance with NRS 338.1385.5, a public body or its authorized representative shall award a contract to the lowest responsive and responsible bidder.

Byrd Underground, LLC currently holds a Clark County Business License.