File #: 24-1631   
Status: Passed
File created: 11/25/2024 In control: Clark County Board of Commissioners
On agenda: 12/17/2024 Final action: 12/17/2024
Title: Approve and authorize the Chair to sign Supplemental No. 4 to the interlocal contract between Clark County and the Regional Flood Control District to increase total funds for design of the Flamingo Wash between the Union Pacific Railroad and Hotel Rio Drive project. (For possible action)
Attachments: 1. Staff Report, 2. RFCD Supplemental No. 4 - Flamingo Wash, UPRR to Hotel Rio Dr

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 4 to the interlocal contract between Clark County and the Regional Flood Control District to increase total funds for design of the Flamingo Wash between the Union Pacific Railroad and Hotel Rio Drive project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.992

Fund Name:

Public Works Regional Improvements/RFCD

Fund Center:

1260110001

Funded PGM/Grant:

PW.FCLA10F

Amount:

$75,000

Description:

Flamingo Wash - UPRR to Hotel Rio Dr

Additional Comments:

Initial contract amount was $26,000. Supplemental Nos. 1 through 3 combined amounts increased the contract by $480,000. Supplemental No. 4 increase of $75,000 revises the total contract value to $581,000.

 

BACKGROUND: 

In April 2010, the Regional Flood Control District (RFCD) approved funding for the Flamingo Wash between the Union Pacific Railroad and Hotel Rio Drive project on its annual Ten-Year Construction Program.

Supplemental No. 4 to the interlocal contract increases total funds for design to cover consultant design services for the additional hydrologic analysis that were performed to evaluate flows along Flamingo Road between the Flamingo Wash and Valley View Boulevard, alternative alignment evaluations for regional facilities to minimize both present and future cost to the master plan, and additional design to be able to reduce/eliminate the acquisition cost to the project associated with the Union Pacific Railroad. This fourth supplemental contract will also extend the project completion date from June 30, 2025 to December 30, 2026, to complete design and provide support through construction.

RFCD approved the fourth supplemental contract at its meeting on November 14, 2024.

The District Attorney's Office has reviewed and approved the fourth supplemental contract as to form.