Title: Approve and authorize the award of Project 20102, Laughlin Lift Station No. 2 Force Main Rehabilitation, to the lowest responsive and responsible bidder and authorize the General Manager to sign a contract contingent upon the submission of required bonds and insurance. Staff recommends award to Harber Company, Inc. dba Mountain Cascade of Nevada (Michael Duke, President); or take other action as appropriate. (For possible action)
Attachments: 1. Staff Report, 2. 20102 Disclosure of Ownership - Harber Co
Date Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

CLARK COUNTY Water Reclamation District

Board of Trustees

AGENDA ITEM

 

Petitioner:

Thomas A. Minwegen, General Manager

Recommendation: 

title

Approve and authorize the award of Project 20102, Laughlin Lift Station No. 2 Force Main Rehabilitation, to the lowest responsive and responsible bidder and authorize the General Manager to sign a contract contingent upon the submission of required bonds and insurance. Staff recommends award to Harber Company, Inc. dba Mountain Cascade of Nevada (Michael Duke, President); or take other action as appropriate. (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

Capital Funds

Fund Name:

CCWRD General Funds

Fund Center:

CCWRD Funds

Funded PGM/Grant:

N/A

Amount:

$16,892,700

Description:

Laughlin Lift Station No. 2 Force Main Rehabilitation

Additional Comments:

N/A

 

BACKGROUND: 

Project No. 20102, Laughlin Lift Station No. 2 Force Main rehabilitation will install dual 16-inch diameter force mains totaling approximately 22,600 linear feet of pipe, a new flow meter vault, a new surge tank, 500 linear feet of 60-inch diameter steel casing with dual 16-inch diameter carrier pipes, and new 60-inch, 72-inch and 84-inch diameter manholes; rehabilitate approximately 4,800 linear feet of 21-inch diameter gravity sewer by cured-in-place pipe; remove and install a new diversion structure and bypass screening structure; and remove approximately 11,300 linear feet of existing force main. This project also includes facility additions and upgrades to the fire suppression system at the Laughlin Water Resource Center's Administration Building.

A request for bids was published on October 21, 2025, in the Las Vegas Review Journal, and posted to the District's website and the Nevada Government Marketplace (NGEM). Bids were received and publicly opened on December 11, 2025, at 2:00 PM. Five (5) bids were received:

BIDS RECEIVED
                                                                                   BID AMOUNT
Harber Company, Inc. dba Mountain Cascade of Nevada          $16,892,700.00
Target Construction, Inc.
                                                                      $19,101,409.00
TAB Contractors, Inc,
                                                                                   $19,366,693.00
Las Vegas Paving Corporation
                                                                      $21,885,596.00
Vegas Civil, LLC
                                                                                   $31,464,348.00

In accordance with NRS 338.1385(5), if the governing body or its authorized representative has advertised for or requested bids in letting a contract, the governing body or its authorized representative must award the contract to the lowest responsive and responsible bidder.

Staff recommends the Board approve the selection of and authorize the General Manager to sign a contract with Harber Company, Inc. dba Mountain Cascade of Nevada as the lowest responsive and responsible bidder. Harber Company, Inc. dba Mountain Cascade of Nevada holds a Clark County business license.

This agenda item has been reviewed and approved by the District General Counsel.