Share to Facebook Share to Twitter Bookmark and Share
File #: 22-1106   
Status: Agenda Ready
File created: 7/20/2022 In control: Clark County Board of Commissioners
On agenda: 8/2/2022 Final action:
Title: Approve and authorize the Chair to sign Interlocal Contract No. 3045 between Clark County and Regional Transportation Commission of Southern Nevada for the Hacienda Avenue between Rainbow Boulevard and Decatur Boulevard project. (For possible action)
Attachments: 1. Staff Report, 2. InterlocalContractOrg 3045 RTCSN HaciendaRainbowDecatur

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Interlocal Contract No. 3045 between Clark County and Regional Transportation Commission of Southern Nevada for the Hacienda Avenue between Rainbow Boulevard and Decatur Boulevard project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R00116E

Amount:

$8,000,000

Description:

Hacienda - Rainbow to Decatur

Additional Comments:

RTC will provide funding in the amount of $8,000,000 for all costs associated with this project.  Clark County is not obligated to pay any of the project costs.

 

BACKGROUND: 

The Regional Transportation Commission of Southern Nevada (RTC) has approved Interlocal Contract No. 3045 and budgeted funding for the Hacienda Avenue between Rainbow Boulevard and Decatur Boulevard project in RTC's Highway Improvement Fund for Fiscal Year 2023.  The design is 90 percent complete and all necessary rights-of-way have been obtained for this project.

The attached Interlocal Contract No. 3045 allocates funds for construction of the Hacienda Avenue between Rainbow Boulevard and Decatur Boulevard improvements project consisting to include pavement rehabilitation, Americans with Disabilities Act upgrades, signage and striping, utility adjustments, sidewalk, curb and gutter repairs, signal modifications, and Intelligent Transportation System infrastructure, and other appurtenances necessary to construct a complete and functional project.  The time of performance is effective to December 31, 2027, unless time extensions are granted.

RTC approved the interlocal contract at its meeting on July 14, 2022.

The District Attorney's Office has reviewed and approved the interlocal contract as to form.