Title: Approve and authorize the Chair to sign Supplemental No. 3 to Interlocal Contract No. 1212 between Clark County and Regional Transportation Commission of Southern Nevada to increase total funds for the Traffic Signal Improvements Program: Package 103 project. (For possible action)
Attachments: 1. Staff Report, 2. Supp 3 Contract 1212 RTCSN TrafficSignalImprovsProg103

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 3 to Interlocal Contract No. 1212 between Clark County and Regional Transportation Commission of Southern Nevada to increase total funds for the Traffic Signal Improvements Program:  Package 103 project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

4990.991

Fund Name:

Public Works Regional Improvements/RTC

Fund Center:

1260110001

Funded PGM/Grant:

PW.R211CFT

Amount:

$280,000

Description:

Traffic Signal Improvements Program:  Package 103

Additional Comments:

Initial contract amount was $4,400,000 and Supplemental Nos. 1 and 2  combined amounts increased contract by $2,000,000.  Supplemental No. 3 increase of $280,000 revises the total contract value to $6,680,000.

 

BACKGROUND: 

On August 13, 2020, the Regional Transportation Commission of Southern Nevada (RTC) approved Interlocal Contract No. 1212 for the Traffic Signal Improvements Program:  Package 103 project on its annual Capital Improvement Plan from Fuel Revenue Indexing Extension Funds.

On September 15, 2020, the Board of County Commissioners approved Interlocal Contract No. 1212 with RTC to provide funds for engineering and two supplementals to the interlocal contract increasing total funds for additional engineering and construction for Change Order No. 1 with Unicon LLC, Bid No. 605722-20, Traffic Signal Improvements at Various Locations #103A - Durango Drive and Gomer Road and Spencer Street and Wigwam Avenue.  On August 17, 2021, the Board approved the aforementioned Change Order No. 1.

The attached Supplemental No. 3 to this interlocal contract increases total funds for construction for the project.

The requested additional funds for this project are budgeted in RTC's Highway Improvement Acquisition Fund - Fuel Revenue Indexing for Fiscal Year 2023.  RTC approved the third supplemental contract at its meeting on September 8, 2022.

The District Attorney's Office has reviewed and approved the third supplemental contract as to form.