File #: 23-399   
Status: Agenda Ready
File created: 3/16/2023 In control: Clark County Board of Commissioners
On agenda: 4/4/2023 Final action:
Title: Approve and authorize the Chair to sign Supplemental No. 2 to the interlocal contract between Clark County and Regional Flood Control District to extend the contract term for the Silverado Ranch Detention Basin, Collection and Outfall project. (For possible action)
Attachments: 1. Staff Report, 2. RFCD - Supp 2 - Silverado Ranch Detention Basin

CLARK COUNTY BOARD OF COMMISSIONERS

AGENDA ITEM

 

Petitioner:

Denis Cederburg, Director of Public Works

Recommendation: 

title

Approve and authorize the Chair to sign Supplemental No. 2 to the interlocal contract between Clark County and Regional Flood Control District to extend the contract term for the Silverado Ranch Detention Basin, Collection and Outfall project.  (For possible action)

body

 

 

FISCAL IMPACT:

Fund #:

N/A

Fund Name:

N/A

Fund Center:

N/A

Funded PGM/Grant:

N/A

Amount:

N/A

Description:

N/A

Additional Comments:

N/A

 

BACKGROUND: 

The Regional Flood Control District (RFCD) has programmed funds for flood control improvements.  On March 12, 2020, Clark County and RFCD entered into an interlocal contract for the Silverado Ranch Detention Basin, Collection and Outfall project (No. PW.FCLA38B).  The Board of County Commissioners approved the interlocal contract on April 21, 2020. 

The Board and RFCD previously approved one supplemental to the interlocal contract decreasing total funds for construction for the subject project.

The attached Supplemental No. 2 to the interlocal contract extends the term of the contract for the project to June 30, 2024, unless further time extensions are granted.  The current total contract value for the subject project is $19,500,000.

RFCD approved the second supplemental contract at its meeting on March 9, 2023.

The District Attorney's Office has reviewed and approved the second supplemental contract as to form.